Installation Instructions Model 801 Expansion Joint

Read instructions before starting installation* For purposes other than water, contact JCM Industries for application and product assistance. Review of Stainless Steel Fastener Management on the reverse will assist with installation.

1. Clean and scrape pipe. Remove any scale, pipe wrap, debris or dirt that may interfere with the complete sealing of the gasket. Inspect pipe for integrity, size, outside diameter and surface irregularities. Confirm the proper size and range of expansion joint and end connections. Inspect fitting to ensure all parts are included. For fittings furnished with stainless steel fasteners, see reverse for fastener management. 2. Lubricate the pipe and the fitting gasket with soapy water. Do not use oil base pipe lubricant. 3 . Pipe alignment is important for proper functioning of the expansion joint, and to ensure free and concentric movement of the slip pipe through the stuffing box. Alignment guides should be provided to allow free pipe movement along the axis, and to prevent horizontal or vertical movement. The first alignment guide should be placed as close to the joint as is practical, up to maximum of 4 pipe diameters. The distance from the first guide to the second should not exceed 14 pipe diameters. If anchors are used, they too should be located within 4 pipe diameters of the expansion joint. Additional supports are usually required in accordance with standard practice. Limit rods are required on long pipelines where two or more expansion joints are required and it is impractical to install intermediate anchors between joints. In other words, the limit rods control the amount of outward movement (pipeline contraction) that can take place in any one joint. Note: All joints except the expansion joint must be restrained joints for the expansion joint to cycle properly. INSTALLATION GUIDE Place the slip pipe to the full entry position in the sleeve body. Withdraw the slip pipe to the calculated value determined by the following formula: Max. Temp. - Installation Temp. x 10* = Total Slip Pipe Total Temp. Range - (Max. - Min. Temp) Withdrawal (Inches) *If joint is made for movement other than 10”, substitute the figure for which joint is designed. EXAMPLE: INSTALLATION TEMP. = 80°F

MAX. OPERATING TEMP. = 130°F MIN. OPERATING TEMP. = 30°F

FORMULA CALCULATION:

130 - 80 X 10 = 50 X 10 = 5” Total Slip Pipe Withdrawal (Inches) 130 - 30 100

2 - 1/2” Withdrawal on each end of double expansion joint

When the slip pipe is in proper position, tighten the bolts on the packing ring, alternating in a star pattern. Tighten to approximately 20 ft. lbs. or until stuffing box packing is tight enough to prevent leakage .

INT801-0115

*Ensure fitting is suitable for application (confirm size, materials, pressure ratings, line content, meets local governing & association standards, etc.). Pipeline operation forces, including pressure fluctuations, thermal expansion/contraction, movement/shifting, etc. will influence the success of the application. Proper anchorage, restraint, harnessing, thrust blocks or other devices must be provided to prevent pipe movement (lateral, angular, axial) or pipe pullout from the bolt-on fitting. Inspection of the pipe integrity is the responsibility of the end user. JCM recommends the use of calibrated torque wrench. Failure to follow installation instructions will result in voided product warranty. For application review or questions contact JCM Industries at 1-800-527-8482, 903-832-2581